Primo Paving was established in 1967 and even today it is still owned and operated by the Bruno Family. Our staff provides nothing but professional paving services throughout the greater Toronto area.
Primo Paving is a proud member of the Better Business Bureau.
Step 1
Choose a contractor and set an estimated time frame. (Don’t Be Fooled By Exact Dates)
Step 2
The old Driveway should be removed in order to inspect the condition of the base. Any contaminated areas must be removed.
Step 3
Edges must be “Trimmed” to ensure straight and proper shaped edges.
Step 4
¾” stone should be added if necessary to give the driveway a proper grade.
Step 5
The driveway should be compacted properly using heavy rollers.
Step 6
Depending on the condition of the driveway and time of year; the driveway can be left to sit for 4-8 weeks, if required.
Step 7
The Asphalt should be spread using an asphalt spreader to ensure uniform thickness as well as a highway finish.
Step 8
The asphalt is then powered using static rollers to ensure proper compaction and proper finish.
Step 9
Depending on the humidity; 4-8 days is the expected waiting period before driveway usage.